When safety and efficiency are critical, smart engineering solutions make all the difference. In this case study, we examine how FRP Engineering assisted a leading chemicals plant in Kwinana, Western Australia, in resolving a challenging access issue — quickly, safely, and cost-effectively — utilising our proven FRP pedestal and grating system.
The Challenge: Hazardous Access in a Bunded Area
Operators at the plant were working in a newly bunded area, which was filled with essential but exposed pipes and valves. These components lay at ground level, requiring staff to regularly step over potentially live lines, creating a serious trip hazard and safety concern.
The client’s initial plan involved installing a raised floor using FRP support beams and grating, but during consultation, it became clear this would be both complex and time-consuming due to the maze of pipework.
Our Approach: A Simpler, Smarter Solution
Instead of a traditional framework, FRP Engineering recommended using our modular FRP Pedestal System — a faster, more flexible alternative.
Here’s how we delivered:
-
Initial Consultation: Identified the risks and assessed the installation environment.
- Site Measurement: Conducted detailed on-site measurements to ensure a precise fit.
- Custom Design: Created shop drawings and prefabricated all FRP grating offsite.
- Rapid Installation: Delivered and installed the system over just two days, with no hot works or operational downtime.
By prefabricating the grating panels to fit the exact dimensions of the site, we were able to minimise onsite work and avoid complications caused by the existing infrastructure.
Products Used
- FRP Pedestals – Lightweight, non-corrosive, and easy to install
- Moulded FRP Grating – Strong, slip-resistant flooring ideal for industrial use
- FRP Engineering Expertise – From consultation to completion
The Outcome: Safe, Clean, and Efficient
The result was a raised, level walkway that eliminated trip hazards and improved operator confidence. The entire area is now easier to navigate and maintain, and the project was delivered ahead of schedule with minimal disruption.
Key Benefits:
- Installed in 2 days
- No hot works required
- No interruptions to plant operations
- Reduced safety risks for operators
- Lower overall project costs
What’s Next?
Impressed by the outcome, the client has engaged FRP Engineering for additional platform and access projects at the site, continuing our mission to create safer, more innovative industrial environments.